  • I did a clone of your data voyages event and updated a few things - I noticed that the dates in the backend are not the same as the dates that end up on the calendar - I put 29 July - 31 July but the calendar is showing 29 July - 1 August - it seems to be adding a day, I think. 
  • https://dsi.dev.umn.edu/events/science-apple-cultivation-test-2

Comments & Events

Xoliswa Shandu, Matogen Digital
Roger that Robyn, Project Manager at Matogen Digital Robyn , thank you for the screenshots. I'll look into it
Robyn, Project Manager at Matogen Digital ❤️